Querry related to P3 import to P6.V7
In the Open Standard
Babu PSMember for 15 years 4 months
- Created
- 1
- 13
0
Hi,
I have P6.V7 installed in my laptop.
I need some of the templates in P3 to be opened in P6.
...tried the following:
1) opened P6 and selected file import
2) selected Primavera Project Planner P3
3) Browsed the folder where P3 files are kept
Got the following message: 'an application event has been intercepted. please note the event code for reference'
event code:ICSPI-1034-6
Can we fix this so that the P3 files can be opened in P6?
Thanks,
Babu P S
1 reply
Oldest firstLog in or join to reply