ora-12952 Error

Ronnel Anthony CelerioMember for 18 years 8 months
Created
2
1
0

Good day,

Anybody has any sort of idea how to workaround this error

 

EXCEPTION ERROR
 
 
Type Exception
 
Event Code PPUSP-0547-2
 
Description
 
PasteProjectUsingSP returned error-1
 
Error inserting into TASKACTV
 
ORA-12952: The request exceeds the maximum allowed
 
Database size of 4 GB
 
Unable to copy tasks in NEW_WBS
 
Error creating new_wbs
 

 

Thanks,

Ronnel Anthony Celerio

2 replies

Oldest first
  1. 0
    Dieter Wambach ·

    RonnelAfter this action the

    Ronnel

    After this action the size of your projects would exceed the size of your database. If you have no own Oracle or MS SQL Server a light version will be installed automatically together with P6. 

    Delete projects or baselines, then it will work.

    Regards

    Dieter

  2. 0
    Jash Sales ·

    Hi Ronnel, If you are copying

    Hi Ronnel,

    If you are copying a project dont paste into the same project as it cant create the same activity ID in your new wbs. Try to paste it in the EPS name and not the project itself by highligting the EPS name then click paste.

    Cheers

    jash