Hi
Iam preparing aschedule with about 30000 activity. Gave this file to my consultant later I added some relations for some activities. How to give the consultant only the relations which changed to enable him from updating the copy which I gave to him previously??
I tried claim digger but I always recive event code error B6572355 which I don’t understand what is the meaning of it.
My primavera is P6.7
Any quick solution will be appreciated.
Hosam