Why the baseline project start change when I do F9

walid LahianiMember for 15 years 11 months
Created
4
1
0

Good morning,

Normaly ,baseline dates don't change when we update!?

Thanks

4 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Walid, You might have

    Walid,

    You might have assigned the current project as your baseline.

    Please investigate.....

     

  2. 0
    walid Lahiani ·

    Yes,In Project->Assign

    Yes,

    In Project->Assign baseline->My choice was current project and now I changed it to Target which I did with Project->maintain baseline

     

    Thank you

  3. 0
    Forrest Chen ·

    right click on gant chart

    right click on gant chart ----- choose 'Bars' ---- find the column named 'timescale' ----- change whatever is chosen into 'project baseline' (same row as project baseline)

    cheers

  4. 0
    walid Lahiani ·

    Good morning,I did right

    Good morning,

    I did right click,bars,i checked primary baseline,so I had the bar target graphic

    thanks,