Baseline Plan ?

Ravirg GehlotMember for 15 years
Created
4
1
0

Hello . I am facing a problem with baseline ...I have Maintained & assigned the baseline the Schedule ..but when I am sending this schedule by importing it to .xer file & sending it to my client via mail , When Client open  the schedule then there is no baseline maintained & assigned is showing....

Can any one tell me how to send the schedule with baseline ...

4 replies

Oldest first
  1. 0
    Kashif Khan ·

    why dont you pdf it?

    why dont you pdf it?

  2. 0
    Ravirg Gehlot ·

    no client require .xer file

    no client require .xer file not pdf

  3. 0
    Kumar S ·

    Dear, sad thing is that there

    Dear,

    sad thing is that there is no option to export the bseline schedule with the current schedule.
    you have to Remove the baseline schedule from the current schedule and export both the schedules seperatly.Just name the schedules accordingly and tell the cleint to import both the schedules and then assign the bseline schedule to the current schedule

     

    cheers

  4. 0
    Amit Parmar (PMP) ·

    Hi ravirg,I agree with kumar.

    Hi ravirg,

    I agree with kumar. You will have to take out the baseline and export both the project seprately. Primavera does not export baseline with the current schedule.

    Regards

    Amit

    Check out my blog on Primavera at http://www.primaverablog.in http://www.primaverablog.in