Skip to content

Displaying Earned Value

Tony NewmanMember for 15 years 8 months
Created
1
1
0

I have a baselined project (using P6) with assigned progress and actuals (in labour hours) but all earned value fields show zero. Other projects with the same settings are displaying the expected EV so I assume it is not an issue based on user or enterprise settings. Can any one suggest a cause for this?

Thank You.

1 reply

Oldest first
  1. 0
    Johannes Vandenberg ·

    Hi TonySuggest to check

    Hi Tony

    Suggest to check baseline settings.

    Baseline needs to be Maintained, same as "created" and needs to be assigned. If you do not assing, earned value shall not be displayed.

    Johannes

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?