P6 start & finishes fixed
In the Open Standard
Bill OBrienMember for 19 years 7 months
- Created
- 6
- 3
0
I am creating a revised target program. I have a number of activities which start dates are pushing out past the data date or will not fix to the date I assign. These activities have no constraints and no relationships! Something is driving them but it is unclear what. The start and finish dates show a star symbol even though no constraints or relationships are assigned? Has anyone come across this before?
6 replies