P6 start & finishes fixed

Bill OBrienMember for 19 years 7 months
Created
6
3
0

I am creating a revised target program. I have a number of activities which start dates are pushing out past the data date or will not fix to the date I assign. These activities have no constraints and no relationships! Something is driving them but it is unclear what. The start and finish dates show a star symbol even though no constraints or relationships are assigned? Has anyone come across this before?

6 replies

Oldest first
  1. 0
    Bill OBrien ·

    @#)

    @#)

  2. 0
    Kannan CP ·

    Bill,Check the Planned Start

    Bill,

    Check the Planned Start dta and the Data Date.

    Kannan

  3. 0
    Frederic Fasquelle ·

    Bill,I faced the same issue:

    Bill,

    I faced the same issue: Star symbol on finish dates while no constraint was assigned.
    It was coming from field "External finish date". Indeed, when some inter-project relationship are lost, P6 is constraining Early/late dates. Like this, it is artificially keeping time logic.

    To recover a proper schedule, add column "External finish date" and manually remove date within cells.
    Launch calculation, everything should be OK,

    regards

  4. 0
    Aldrin Morallos ·

    Bill, Try to open up the

    Bill,

     

    Try to open up the Predecessor or Relationship Column.

  5. 0
    Bill OBrien ·

    Just checked my External

    Just checked my External links and your correct.

    Frederic your a legend, thank you very much.

    Its always somthing simple....

  6. 0
    Anning Sofi ·

    There are other ways to clear

    There are other ways to clear the external links, but Frederick method is quick and simple.