Attachment PDF file in Note

Phansuek KulapMember for 14 years 5 months
Created
2
2
0

Hello all Planner 

       I'm using P6; Release 6.0. In the Notebook of each activity, that we can attach our note such as Picture and Link. But this function  unable to attachment PDF file. I would like to attach PDF files for for information as I can convert Auto CAD file to PDF and some documents can also be converted to PDF file.

       Anyone,known about this option or you have another way to attach PDF file in you schedule.

 

Big Thankyou

 

 

 

 

 

2 replies

Oldest first
  1. 0
    Justin James ·

    Dear Kulap,For uploading your

    Dear Kulap,

    For uploading your pdf documents , you should use "Wps&Docs" tab at the bottom , Not the Notebook option.

    Regards

    Justin,

    Qatar.

  2. 0
    Phansuek Kulap ·

    Thanks so much Justin James

    Thanks so much Justin James