How to report progression by meters 3 (m3)?
In the Open Standard
Charles CharlesMember for 14 years 3 months
- Created
- 5
- 1
0
Hi Everyone
I am working in a project that requires earth works. My manager wanted me to show him, the progression complete % based on the m3 that we have completed.
For example:
We got 1000(m3) need to be done in 1 months. If my actual is 200(m3), then we have done 20%. (This is like the outcome of my resources), what do i need to do in P6 to make it showing, -20% progression other than I compulate myself and put the amount in physical completion?
My own solution
I create a material "reasource". named "project completion". In unit there, i put 1000m3, price = 1, then i update it everyweek. It is just a temperory solution, because i got deadline to produce this plan.... but i realised that when i run a report on total resource, my total budget will be out, because the resouces report included this "project completion resources, which shouldnt be).
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?