Question about report

Scott ParkerMember for 14 years 2 months
Created
1
1
0

My client wants me to submit a three week look ahead using the following format.  I was wondering if anyone can help me create it in P6.  Thank you in advance

 

Sample Report

 

1 reply

Oldest first
  1. 0
    Gary Whitehead ·

    You can'tcreate that in P6

    You can'tcreate that in P6 -You can only display baseline/planned/actual dates in columns and not rows.

     

    You'll have to export the data to excel, and then juggle it around into the right format.