Re: Importing Issues for Microsoft Project.

Tom GouldburnMember for 14 years 1 month
Created
1
4
0

Hi Guys,

Hope all is well? After abit of assistance if you can.

I'm currently a young Junior Planner having difficulty importing a Microsoft Project file into the P6 version 7 Programme.   

I've got a MPP 2003 file format all ready and what I'd like to do is import. Difficulty I'm having is that MPP is not a valid importing format I think. The requested format is XML/MPX When I go to save the format in project to a XML and import it I get a error message after the process is completed.

Would any of you guys be able to give me some assitance as I'm not sure if I'm following the releavant steps?

Regards,

Tom Gouldburn

1 reply

Oldest first
  1. 0
    Paul Harris ·

    TomHave you any blank lines,

    Tom

    Have you any blank lines, if so remove them before saving as a XML file, this in my experiance is a show stoper for importing into P6.

     

    If you want to see the issues when importing a MSP file into P6 there is a Technical paper on my websites.

    Paul E Harris
    Eastwood Harris Pty Ltd
    www.eh.com.au,  www.eastwoodharris.com and www.primatrain.com.au
    Project Control Consultants and Planning and scheduling software book and training manual publishers

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?