Planned start & Finish change

Siva GaneshMember for 14 years 10 months
Created
0
2
0

Dear friends,

 
Activity 1 ---FS---- Activity 2
 
Activity 1 - Start date 25 jul-2012
Finish Date 16-aug-2012
 
Later i clicked the check box for Actual start date - 29-jul-2012 and Actual Finish date as 31-aug-2012
 
Activity 2 - Planned start is 17aug-2012
Planned Finish is 21-sep-2012
 
Actual start is 1-sep-2012
Actual finish is 23-oct-2012
 
Now i scehduled today(08-nov-2012), and added column Planned start & Finish and Actual start & finish. The dates under Actuals are same as i entered. But the dates under Planned start was completely different. 
 
And also Activity 1 is not FS relationship with Activity 2. am really confused and dont know what to do. 
Experts kindly help me.
 
Sivaganesh.S

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?