Import/Export
In the Open Standard
Ariel MalibiranMember for 17 years 7 months
- Created
- 3
- 2
0
Guys,
I have my cost loaded schedule prepared in P3. I have made adjustments in cost using the global change then imported the p3 schedule in P6. After the successfull importing to P6, I noticed that the cost remains the same as if I have not made adjustment thru global change in P3. Also, the budgeted quantities have been changed.
please help me in this issue.
thanks,
ariel
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?