Import/Export

Ariel MalibiranMember for 17 years 7 months
Created
3
2
0

Guys,

I have my cost loaded schedule prepared in P3. I have made adjustments in cost using the global change then imported the p3 schedule in P6. After the successfull importing to P6, I noticed that the cost remains the same as if I have not made adjustment thru global change in P3. Also, the budgeted quantities have been changed.

please help me in this issue.

 

 

thanks,

ariel

3 replies

Oldest first
  1. 0
    Ariel Malibiran ·

    Also, I noticed that the

    Also, I noticed that the budgeted quantities have been changed (ie, increased by 8 times the BQ in P3) this is maybe because in P6, 8hrs per days is specified in the User Preferences, Time Units. I'm not certain about this. 

    The odd and big question is, how is that possible that p6 used  the original cost considering that i have already changed the cost using the global change.

    Any idea please!

     

    Regards,

     

    Ariel

  2. 0
    Jose Frade ·

    Ariel. Maybe P6 is not using

    Ariel.

    Maybe P6 is not using the original old values from P3 but is simply making the calculation of quantities and arrving to the same value as P3 (how would P6 import a value that was not available anymore for importing ?).

     

    Check your calendars, resources, units, unit/rate and the explanation is in one or several of these values not matching the imported database

     

    BR

    JMFrade

  3. 0
    Raymund de Laza ·

    You changed the Cost Manually

    You changed the Cost Manually in P3 but the Reosurce Price per Unit is carried with the Resource when exported.

    When Importing, P6 will calculate as Resource Unit x Resource Unit price = Budget Cost.

Log in or join to reply