**URGENT** P6 6.2 Calandar Issues
- Created
- 2
- 2
Hi Everybody,
I have an urgent tender programme I must finish ASAP and my calandar won't calculate correctly.
My base calendar is set at 8hr/day 5 days a week, all my activities that use this calendar are fine (a day = a day)
But when i try to use a 7hr/day 5 days a week it does not calculate correctly, I have set this calendar with a 1 hour lunch break so it starts and finishes the same time as my 8hr day calendar.
If i add an activity using the 7hr/day calendar and put the duration as 1 day it starts at 9am but finishes at 10am the following day.
How do i get this to finish at 5pm the same day?
If you could help me that would be great.
John
2 replies
Oldest firstLog in or join to reply