What dose "As-Built" mean?

Jenny IngcoMember for 14 years 9 months
Created
5
2
0

Dear All Planners,

What dose "As-Built" in engineering terms mean? and what is the diffrent between "As-Built" and "as recorded" which one is best to use?

Thak you,

Hanson

5 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi Hanson Generally As Built

    Hi Hanson

    Generally As Built means the date and time that an activity was carried out.

    As Recorded would be the same as As Built but not commonly used.

    As Planned is the date and time when it was intended to be carried out accoriding to the current programme.

    Best regards

    Mike Testro

  2. 0
    Abubaker Ali ·

    As built drawings are the

    As built drawings are the drawings as they are specifically constructed which may vary from the original design for a number of reasons

  3. 0
    Arun Kumar ·

    As I know"As built" is the

    As I know

    "As built" is the term used for Construction Engineering drawings. 

    If we use any higher section instead of actual designed section shown in drawing then we have to show that actual section in drawing and submitt it to client.

    Example:

    If we have to use Plate 25 mm in Structural steel works, but we used Plate 28 due to shortage of Plate 25. Then we indicate Plate 28 mm in drawings because it is as built in construction. That means it is "As built" drawing.

    Hope u understand.

     

    Arun Kumar 

  4. 0
    Jenny Ingco ·

    Thanks Kumar. Yes, good

    Thanks Kumar. Yes, good example.

  5. 0
    Jenny Ingco ·

    Hi Mike, That was very

    Hi Mike,

     

    That was very helpfull. Thanks a lot.

     

    Regards,

    Hanson

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?