delays/advance (days) ?

Alain De leonMember for 14 years 4 months
Created
1
2
0

What is the easiest way to know delays/advance (days) ? p6

Thanks

1 reply

Oldest first
  1. 0
    Gary Whitehead ·

    1) Create a baseline to

    1) Create a baseline to measure delays / advance from (Project Menu > Maintain baselines)

    2) Assign that baseline to your current project (Project Menu > Assign Baselines)

    3) Show the colums "Variance -BL Project Duration", "Variance -BL Project Finish Date", and "Variance -BL Project Start Date" (View Menu > Columns > "Durations" group)

    4) For a visual represrentation, show the baseline bar in the gantt chart (View Menu > Bars)