P6 Team Member

Analyn BinuluyanMember for 15 years 4 months
Created
1
1
0

For P6 Team Member Users,

Please feedback your experience on P6 Team Member Web and P6 Team Member for iPhone App. For the iPhone App, it is specified in the user's guide that "team members can update assigned tasks on their iPhone, iPad and iPod Touch" but I was able to download and install P6 Team Member on Samsung tablet and galaxy from google play. Anybody tried updating activities using samsung instead of iphones?

Thanks,

AB

1 reply

Oldest first
  1. 0
    Robert Victor Gammill ·

    There are two phone apps-

    There are two phone apps- iPhone and Android. Any organization can use one or the other, but not both phone apps.

    Team Member Web continues to work with either phone app.