Hi

I request you to guide me on the below issue

I have three contractors, one is Engineer and another is Procurement, and Construction, all give their schedule, how I could link all together, first to form a baseline and then periodically, if they send the update, how to replace the old file to new one.

 

please guide

Thanks

Venkat

1 reply

Oldest first
  1. 0
    Deepak Jain ·

    Venkat, You can use P6

    Venkat,

    You can use P6 enterprise server to establish an overall IMS (Integrated Master Schedule) which allows you to set-up a Master and sub nodes beneath for individual EPC contractor plans while also recognising task interdependencies & logical relationships  