Project Finish becomes Early Finish After Scheduling.
- Created
- 4
- 2
Ok, this is baffling me.
The schedule is a month behind where we should be, so i try to reflect this accurately within the programme, and this doesnt want to play ball, the Logic within these activities is sound.
Activity X - Submit Document A, Finish Milestone Date: 03rd March (*A*) - (Early Finish Date: 03 Feb)
FS With..........
Activity Y - Document A Review Period: 03rd March (*A*) to 28th March. (Early Start Date: 03 Feb - Early Finish : 28th Feb)
I have applied actual start date, and an expected finish. When i schedule the programme, even though i have an expected finish on Activity Y, it moves the dates back to Early Start / Early Finish, which is ignoring both its own logic (Starting before its predecessor) and the actual dates / expected finish dates.
So to clarify, when i F9 the programme, activity Y reverts to its initial Early dates, rather than its Actual Start date, and expected finish
I'm sure this is something very simple to fix.
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?