Skip to content

Project Finish becomes Early Finish After Scheduling.

Lee JohnsonMember for 12 years 9 months
Created
4
2
0

Ok, this is baffling me.

 

The schedule is a month behind where we should be, so i try to reflect this accurately within the programme, and this doesnt want to play ball, the Logic within these activities is sound.

 

Activity X - Submit Document A, Finish Milestone Date: 03rd March (*A*) - (Early Finish Date: 03 Feb)

FS With..........

Activity Y - Document A Review Period: 03rd March (*A*) to 28th March. (Early Start Date: 03 Feb - Early Finish : 28th Feb)

 

I have applied actual start date, and an expected finish. When i schedule the programme, even though i have an expected finish on Activity Y, it moves the dates back to Early Start / Early Finish, which is ignoring both its own logic (Starting before its predecessor) and the actual dates / expected finish dates.

 

So to clarify, when i F9 the programme, activity Y reverts to its initial Early dates, rather than its Actual Start date, and expected finish

 

 

I'm sure this is something very simple to fix.

4 replies

Oldest first
  1. 0
    Joe Peck ·

    Hi Lee,   If I understand

    Hi Lee,

     

    If I understand your issue correctly. In P6 you are using the Early Finish and Late Finish columns and they will always show the original early and late finish dates even after actualizing the schedule.  Try using the Start and Finish columns which will give you the correct actual start and finish dates.  Also make sure to move your data date later than the actual start and actual finish dates before you F9.  

  2. 0
    Lee Johnson ·

    Sorry Joe, no, i am using the

    Sorry Joe, no, i am using the start & finish columns, i have only brough in the Early Start & Early Finish columns to investigate the issue.

  3. 0
    Gary Whitehead ·

    1) What's your data date?2)

    1) What's your data date?

    2) Do activites X or Y have any constrains on them? If so, what?

    3) Any lag on the FS relationship between X and Y?

    4) Also, under schedule options, can you confirm:

    a) Is "use expected finish dates" ticked?

    b) Retained logic, progress overide, or actual dates?

     

    Cheers,


    G

  4. 0
    Zoltan Palffy ·

    have you set your project

    have you set your project must finish by date  ?

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?