Remaining cost & Project Cost are after updating

Rajashekar ReddyMember for 12 years 5 months
Created
1
3
0

 

Hi,

I am new to P6, i am finding difficulty cost, in my program if i am updating the % complete of the activity my earned value is getting updated but my total budget cost and remaining cost are same. remaining cost is not getting updated.

1 reply

Oldest first
  1. 0
    Ravi Katare ·

    Hi,Are you updating the

    Hi,

    Are you updating the remaining resource units? If not do it

    - Ravi