P6 V7 Updating a Project using another version of the project
In the Open Standard
Charlie DanielsMember for 12 years 10 months
- Created
- 2
- 4
0
Hi,
Is it possible to use one version of a project, to update only certain activities of a newer version?
I have added more detail to a project, linked it to sub projects, and would like to update this projects dates with that of a newer version that does not have the links to the sub projects, I don't want the update op remove the links to the sub projects in the older version though, which is what is happening when I try this, it updates the logic and everything else too. (removing the links which I would like to keep)
Any suggestions?
Thanks