Error Msg

Ali AlaliMember for 11 years 11 months
Created
2
2
0

Hi Everyone,

I faced an error msg when deleting a project or make a copy of another project as following , I need a solutions please.

*****************************************************
*                EXCEPTION  REPORT                  *  
*****************************************************
Date:          02-Dec-14    
      
Executable:    PM.exe   
Application:   Primavera P6 Professional R8.2 
Event Code:    PRMDB-1567-D   
Message:           
  PRM DBAccess Error: ORA-12952: The request exceeds 
  the maximum allowed database size of 4 GB 
      
      
Context:      
  1: TCFormManager.SetToolbar  
  2: TDevxMainForm.BeforeFormShow  
  3: TfrmLogin.FormCreate   
  4:      
  5:      
  6:      
  7:      
  8:      
  9:      
  10:      
      
Detail:      
  Type:        EprmDBSQLExecutionFailure  
  Object Type: TCVirtualQueryGrid  
      
Database Error:    
   Error Code:     0   
 
   
 
    
      
    
  
    
     
 
  
      
      
      
   
   
    
      
      
      
      
      
      
      
      
      
   
   
      
     
    

2 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    you have reached the 4 gig a

    you have reached the 4 gig a byte memeory limit for microsoft slq express.

    the way to fix this is to open an old project and start to delete a few activiites

    then start to delete a few more activiites 

    this is a long and tedious process bcasue it takes memeory to delete data.

    at some point you wil be able to delete severla activities at the same time

    now you can delete the old projects

    I would recommend creating another database to start any new projects 

     

     

  2. 0
    Ali Alali ·

    thanks sir

    thanks sir