Filtering WBS

Kannan CPMember for 18 years 4 months
Created
7
1
0

Hi all,

By applying filter to the main WBS, is it possible to hide a particular section in the schedule.

For eg: I have a WBS " PROVISIONAL SUM" in the schedule and there are different sub-sub work packages as well and the activities are assigned to these sub-sub work packages.

 

Similar to the main WBS " Provisional Sum", there are other main WBS like  " DESIGN" , " ENGINEERING", " PROCUREMENT " etc.

I want to hide the full WBS"PROVISIONAL SUM" by creating a filter : WBS not under " PROVISIONAL SUM".

I Know that I can make the filter" WBS under " DESIGN", "ENGINEERING" etc.

But, is it possible to make a filter as highlighted above?

Best Regards

Kannan

 

 

 

7 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    instead of using not under

    instead of using not under did you try

    filter where ALL

    wbs not equal to PROVISIONAL SUM

    wbs not equal to DESIGN 

    wbs not equal to ENGINEERING

    wbs not equal to PROCUREMENT

  2. 0
    Kannan CP ·

    Hi Zoltan,I already tried it

    Hi Zoltan,

    I already tried it with Filter " WBS not equal to Provisional Sum". Since there are many work packages under this WBS and moreover the activities are assigned under these work packages, it is not working.

    Other wise I have to work with options as follows;

    1. Filter with WBS not equal to Work Package 1, WP2 WP3 etc

    other option

    2. Filtering to see only the other Main WBS: like WBS equals to Engineering, WBS equals to Procurement, WBS equals to Construction etc. If there are lot of main WBS it will be required to type it one by one.

    Best Regards

    Kannan

  3. 0
    Raymund de Laza ·

    Hi, I suggest to remove the

    Hi,

    I suggest to remove the indent of WBS level in the Group and Sort window.

     

    Regards,

  4. 0
    Kannan CP ·

    Hi Raymund,I think in that

    Hi Raymund,

    I think in that case the hierarchy of WBS will be lost and will not be in the order of Original WBS.

     

    Regards

    Kannan

  5. 0
    Zoltan Palffy ·

    how about ANY where wbs name

    how about 

    ANY 

    where wbs name does not contain PROVISIONAL SUM

    where wbs name does not contain DESIGN

    where wbs name does not contain ENGINEERING 

    where wbs name does not contain PROCUREMENT

  6. 0
    Kannan CP ·

    Hi Zoltan,Its working with

    Hi Zoltan,

    Its working with the Filter :- WBS Path   does not contain PROVISIONAL SUM.

    Thanks for your help.

    Regards

    Kannan

  7. 0
    Zoltan Palffy ·

    no problem

    no problem