dear all ,

Please  i want to remove a ressource assignement from tasks by global change (to be quiquely) wich formula suitable.

thanks

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    you can not delete it with

    you can not delete it with global change only change it 

    the fassest way to do what you want is to 

    filter for all of the activiites that you want to remove the resource assignments

    select edit select all

    right click select Assign then select resources

    then select the resource that you want removes and click on the red X box on the right had side of the screen

Log in or join to reply