When I make down the original duration , the ressource allocation became overloaded but the unit/TIME didn't change

walid LahianiMember for 15 years 11 months
Created
3
1
0

Hello ,

Explication :

Imagine we have a Labour who works 8h/day and an excavation task ,

the original duration of the task is 10 days

so ,this laber will work a total of 80h ,

If i change the original duration to 2 days ,normally this laber have to work  40h/day => 5 labers/ day

But in the table we have always 8h/day (unit/time) =>one laber only

Thank you

 

 

3 replies

Oldest first
  1. 0
    Shareef Abdul Azeez ·

    Hi Wahid, In your case,

    Hi Wahid,

     

    In your case, before changing duration to 2 days ,,,set Duration Type: Fixed Units.

    Then change duration.

     

    Best Regards

    Shareef A Azeez

  2. 0
    walid Lahiani ·

    Thank you !   Why I have to

    Thank you !

     

    Why I have to choice fixed Unit and not another type (physical,.....)

    I mean how we choice the type : fixed unit or fixed duration,....

    thanks

  3. 0
    Shazia khan ·

    Please check your

    Please check your calennder

     

    it set to 8 hr per day or 10 hr per day.

     execavation is a construction activity, in general construction activity  time is 10 hr per day. (site working time 10 hr per day)

     

    and Engineering main office  worked 8 hr per day , 5 or 6 days per week

     

    first you check calender. ( ste hr / day  week, Month , & years)

    2nd assign a right cal to activity

    3rd check admin preference setting.

    may it can work for you.