Skip to content

Multiple projects for each part of project

Martyn CoatesMember for 19 years 2 months
Created
0
3
0

Hi any help appreciated with this.

 

I changed projects and my predecessor to my role has created a project for each major part of the WBS instead of an overall project.

 

Obviously there linked between and I can open all at once but are there any differences or anything I need to watch out for dealing with this multi project for 1 project?

 

an advised way of putting all into 1 would be appreciated, I was going to create a new one, create a wbs and open all in 1 then move out of each project into new wbs.

 

any comments appreciated

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?