Show predecessor project ID

Thomas NicholsonMember for 20 years
Created
1
3
0

Morning all,

I have a portfolio of work with links to a contractors projects, unfortunately however they have changed their project number so my links no longer work.  As I have 100 projects with such links I want to check which have been affected and which haven't so I can update them with the new project ID number.  However I can't seem to see a way of getting P6 to show me either in a column view or via a report the preceding activities project ID only the activity number.

Does anyone know how I get P6 to show me this information to save me going through each activity with links to see where it's linked to?

Thanks

Thom

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    here are your options option

    here are your options 

    option #1

    while in the relationship tab either in the predecessor window or the successor window you can add the project id as a column right click and select customize predecessor columns or customize successor columns and from the Available Options on the left expand the General category and select Project ID.

    Option  #2

    Also you can export the relationships to excel and the relationships will have the associated Project ID number. 

    So export the relationships prior to the changes then export the relationships after the changes and do a Vlookup in excel and see what has changed.

    Option #3

    Just change the project number back to what it originally was. 

     

Log in or join to reply