How to display No of Days in a month in TimeScale

Jagjit SinghMember for 10 years 4 months
Created
2
2
0

Hi

 

   How to display No of Days in a month in TimeScale considering 30 days as 1 month . I want to display like this in TimeScale and draw Gantt Chart accordingly

30        60          90         120        150        180  & so on till 450

 

Thanks

2 replies

Oldest first
  1. 0
    Jagjit Singh ·

    Hi   Currently it is

    Hi

     

      Currently it is displayed as  Jun 2016 , August 2016 , Septemeber 2016 and so on

  2. 0
    Zoltan Palffy ·

    view timescale then at the

    view timescale 

    then at the bottom 

    ordinal dates 

    then ordinal date interval is days