How can I see planned AND remaining work in the same report?
In the Open Standard
Alex GarciaMember for 10 years
- Created
- 8
- 4
0
If I am running a cost loading report out of a status project, for the purposes to inform my customer what unfinished work is remaining on the project, and how it is time phased, I am only seeing BCWS. The remaining work of the in progress activities doesn't show up on the report, so I am short on budget.
How can I get both planned and remaining to show up on the same report, with time phasing represented as it stands in the status project?
Thank you!
8 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?