Planned Labor Costs
- Created
- 2
- 3
Hi all,
I'm trying to have an activity with a set labor cost.
This is a cost that has been agreed upon for the activity and shouldn't change.
Staff record to a timesheet. Different staff have different rates.
My problem is that when applying actuals planned labor cost and at complete cost changes to resource rate x planned units I think and at complete is changed to the actual cost.
Is there anyway to just set a planned and at complete cost for an activity, and only have remaining change as actuals are applied?
Edit:
How is remaining labor cost supposed to work? Anytime I increase the actual units, At Completion Labor Cost increases by the same amount so Remaining Labor Cost never changes?