P6 R8.4 Default Project Settings
In the Open Standard
Casey FMember for 10 years 4 months
- Created
- 2
- 3
0
I am running P6 R 8.4 is there a way to change the settings default when a new project is created? I am looking to set the default of define critical activites as longest path instead of Total Float less than or equal to. I work with a variety of skill levels with P6 and it would save a lot of wasted time if I can set the default critical activities to longest path.