Cost Loaded Schedule Import Error

Zahid ShaikhMember for 10 years 1 month
Created
3
2
0

When I Import my Cost Loaded Schedule from One Computer to another the Cost from Project Reduces..

Cost for Many activities goes missing.

But the main computer in which the Cost Loading was done, If I import it again on the same computer Cost comes correct

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    which costs are we talking

    which costs are we talking about budgeted, actual, actual at completion which one ?

    also check your filter make sure that it is set to ALL

    also go to Projects directory make sure you project is highlighted 

    got to the calculations tab 

    on the right under the Resource Assignments make sure that Add actual to remaining is checked.

    also during the import process make sure that in the Update Project Options that select modify

    under the Data Type Activity: make sure that the action for activity resource assignment is set to insert new

    under the Data Type Global: make sure that the action item under resources is set to insert new

  2. 0
    Zahid Shaikh ·

    Budgeted Total cost goes

    Budgeted Total cost goes missing.

     

    I will try using the add new resource setting.

  3. 0
    Zoltan Palffy ·

    that should work

    that should work 

Log in or join to reply