import/export activity code

Jason LIMember for 18 years 9 months
Created
3
2
0

Dear All,

I'm preparing the schedule by system, using activity code. there are thousands of system and subsystem, are there any quick way to import/export the activity code from excel.

 

thanks

3 replies

Oldest first
  1. 0
    Wullie Hendry ·

    Use SDK

    Use SDK

  2. 0
    Emad Mofarej,PMP,PSP,CDT,CCM ·

    OR XERfileparserHowever if

    OR XERfileparser

    However if you want to transfer activity codes from a project to another you can use update baseline function in P6

  3. 0
    Zoltan Palffy ·

    this is a 2 step processstep

    this is a 2 step process

    step 1 is buildign the activity code dictionary. The fastest way to build this is by using SDK

    step 2 is populating the activites with the proper code value. The fastes way to do this is to export all of the activities along with the code fields  and then populate the code value fields in excel and import the excel file back into p6