Sonya CortezMember for 8 years 11 months
Created
10
4
0

I have saved an MS Project as an XML file. I want to import it into P6, but the Primavera P6 - XML option is greyed out when I go through the import dialog. Is there a way to fix this, or a better way to get an MSP project into P6 (with logic).

Also, my MSP will not allow me to save or export as an MPX.

10 replies

Oldest first
  1. 0
    Tom Boyle ·

    Sonya,"Primavera P6 - XML"

    Sonya,

    "Primavera P6 - XML" and "Microsoft Project XML" are two different file types.  Do you have a Microsoft Project button available on the Import Format window?  That's where you should click, then select XML in the pull-down list.

  2. 0
    Phil Bedford ·

    MS Project no longer gives

    MS Project no longer gives the option to save as an MPX file.

    There is a convertor kicking around that apparently convers MPP to MPX, but I cant get it to work (Claims I dont have MSP installed, when I definately do)

    Im having the same issue as you Sonya, I have exported the XML from MSP, but when I import (using the Import Microsoft Project XML option) I get an error that claims the import succeded, but with errors.....and then I cant find the imported file in my Project list!

    For some weird reason, I also cant Export an XLS file from P6, gives me an error about the database or something :(

     

    Sorry for hi-jacking your thread.

  3. 0
    Zoltan Palffy ·

    save the project to an MPP

    save the project to an MPP then run the mpp to mpx and import the mpx

    there are at least 2 mpp to mpx convertes out there 

  4. 0
    Sonya Cortez ·

    The option to import XML is

    The option to import XML is greyed out. I did not have any luck with the MPP to MPX converter.

     

    I did find a solution. I found an application that converts XML to MPX. I was able to export the MSP project as an XML then convert it to MPX and import it into P6 that way.

    I had to try this process a few times since I was having issues with logic and dates in the import. I was able to fix everything by setting a calendar to all of the activities in MS Project.

  5. 0
    Zoltan Palffy ·

    can you please supply that

    can you please supply that link to the xml to mpx cpnverter please 

  6. 0
    Sonya Cortez ·

    Taktone: Project File

    Taktone: Project File Converter

    https://www.taktone.com/Home/PFC

  7. 0
    Alexandre Faulx-Briole ·

    Sonya,thank you very much for

    Sonya,

    thank you very much for the link to taktone; the converter and the viewer are great!

    Alexandre

  8. 0
    Phil Bedford ·

    Thats the one I used last

    Thats the one I used last night, works a treat.

  9. 0
    Zoltan Palffy ·

    thank you

    thank you 

  10. 0
    Khuong Do ·

    Hi,You can try the convert

    Hi,

    You can try the convert tool from Primavera to convert from mpp to mpx. You can refer to instruction here https://doduykhuong.com/2016/02/04/convert-microsoft-project-mpp-to-mpx-to-import-to-primavera/