Why putting costs in as units instead of cost is easier...
In the Open Standard
John ReevesMember for 13 years 5 months
- Created
- 2
- 3
0
I review many schedules. I used to make many schedules. I have been noticing that many contractors prefer to enter costs as resource units instead of costs. I recall it was better, but I cannot remember why it is easier - any insights into why this is common? I can, and eventually will ask the contractors but I like to be prepared.