Full of Constraints

Suhaib NassarMember for 8 years 3 months
Created
4
3
0

As a bigenner planner, I have made a plan for a client as two projects, the start and finish dates for one of them are the actuals. whereas the start and finish dates of the other one are the planned ones, then I maintained the latter as a baseline to the first one, the client did not accept it and asked to modify that, he has also mentioned that the project is full of constaints. Are there any other ways to follow?

4 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Suhaib,do you mean: you don't

    Suhaib,

    do you mean: you don't use activity relationship, but only activty constraints to schedule your project?

    you should not have any other date constraint that the project start date and the contractual finish date

    Alexandre

  2. 0
    Zoltan Palffy ·

    the only activities that

    the only activities that should have constraints are CONTRACTUAL milestones

    also the project must finish by date should be set 

  3. 0
    Suhaib Nassar ·

    Many thanks, the problem has

    Many thanks, the problem has been solved

  4. 0
    Zoltan Palffy ·

    glad I could help

    glad I could help 