XML import assistance

Rodney JonesMember for 14 years 4 months
Created
4
2
0

Hi Everyone,

 

I am having trouble importing this xml file (from MSP), there are Zero resources, costs, expenses or anything else, just activities, duration, manhours and some text in msp activity text field text10.

 

The import fails on my companies server P6 but won't allow me to view the error log!

 

Would a member please try and import and then export as an xer for me? Hmmmmm, how do I attache the xml file here?

 

Thanks,

 

Rod

4 replies

Oldest first
  1. 0
    Mansoor Sadiq ·

    Let me check the import

    Let me check the import issue, if you can share it at mansoorsadiq@gmail.com

    Mansoor

  2. 0
    Mansoor Sadiq ·

    Let me check the import

    Let me check the import issue, if you can share it at mansoorsadiq@gmail.com

    Mansoor

  3. 0
    Zoltan Palffy ·

    check you messages here

    check you messages here 

  4. 0
    Rodney Jones ·

    All sorted, the msp file had

    All sorted, the msp file had a line item with duration but no text in the Activity Name field, that was causing the import to fail.

     

    Now, how do I close this post?