Skip to content

Updating project plans

Ron BeecheyMember for 24 years 4 months
Created
4
4
0

I am currently in the role of project controls.   I receive from our contractors a weekly update in the form of a file to upload into P6.   Once I have imported or uploaded the project plan I will ensure the milestones are connected and then produce a complete start to finish integrated plan.  Included is a commissioning schedule.  

My question may be simple but is there a way or does the P6 program merge the next week plan replacing only the updated items or does it replace completely deleting the interconnecting links I made to each plan.    All schedulers work on standalone machines and they submit a new file each week.

 

Any help is appreciated. 

4 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    you choose what do to during

    you choose what do to during the update while importing 

    Open the project in P6 then select file import then select xer and then find the file to import 

    during the import options under the Import Action you can choose to Create New Project, Add Into Existing Project, Replace Existing Project or Update Existing Project 

    You can select Update Existing Project 

    Then under Update Project Options select Modify 

    You will now be at the Modify Import Configuration screen

    then you can choose what and how you want to import the information

    There are 3 different categories 

    Data Type: Activity 

    Data Type: Global

    Data Type: Project 

    In each of these categories under the Action column you can choose to Update Existing, Do Not Import, Insert New or Update Existing.

    for Activities you can just select Update Existing and the activities will be updated this this will also update the Activity Relationships and the Activity Resource Assignments

    Under the Gllobal category thsi deals with Resources and can choose if you want to import them or update then you have the same actions available here.

    Under the Project category you can update or add Activity codes, Activity code values, calendars and wbs

    There is a lot of flexibility of how and what you want to import

  2. 0
    Ron Beechey ·

    Thanks for the info.   Big

    Thanks for the info.   Big help I was thinking that this would work but wondered if there was easier methods.   I will be doing this weekly as the contractors submit their updates.  Again thanks for the help.

  3. 0
    Zoltan Palffy ·

    this is the easiest way to do

    this is the easiest way to do this. I would suggest that you keep updating the same project id but BEFORE you update it copy it so you have a historical record for that update period and add the date into the project name.

    for example if the project id is named CAR and is statused as of Feb 1 then prior to updating it copy CAR and name it to

    CAR1-020119

    Now you can add the next months (FEBRUARY) progress to CAR

    Next Month copy CAR to CAR2-030119

    This way all ofyour layouys wont go to wates and can be used over and over again

    This tells you the update # and the date of the update. Its simple but effective

  4. 0
    Ron Beechey ·

    Thanks again for the help

    Thanks again for the help

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?