Project Codes

Ron BeecheyMember for 24 years 4 months
Created
5
2
0

I have 3 projects and all have different Activity Codes for Systems.   I would like to use one common code to be able to group and sort on a layout with all 3 plans.   Can I create a set of codes in one of the projects and then move this to a global level to use with the other 2 project schedules. 

This should have been set up at the beginning but I got into this late. 

5 replies

Oldest first
  1. 0
    Santosh Bhat ·

    Ron, Use EPS Level Activity

    Ron, Use EPS Level Activity Codes, and add the EPS Activity code to Common EPS node under which each project is placed. This way the Activity Codes can be used across all projects and you may use this common code for all grouping and Sorting.

    Of course the same can be achieved by making the activity Code a Global code also.

  2. 0
    David Kelly ·

    Ron,The name that you give a

    Ron,

    The name that you give a project-specific activity code is just the external label. Internally every code has a unique obejct ID. It is unhelpful that Oracle allows you to use duplicate labels. You cannot do what you want with project specific codes. A Global or EPS level code is required.

  3. 0
    Zoltan Palffy ·

    make it a global code

    make it a global code 

  4. 0
    Raymund de Laza ·

    Copy and Paste will do.Copy

    Copy and Paste will do.

    Copy all Activity Project Codes to Activty Global Codes. After copying add a prefix to the Global Codes to make them differ.

  5. 0
    Zoltan Palffy ·

    thats the best way

    thats the best way 