Report - Manhours Planned Vs Actual
In the Open Standard
Jithin KambhikanamMember for 15 years 6 months
- Created
- 3
- 2
0
Hello Everyone,
I have made a resource loaded schedule.
I am looking for report which can Show me Planned Manhours (As per Basline) and Earner Manhours (After Updating the Schedule) and Remianing Manhours (After Updating the Schedule) in Time Distributed Format like below,
| Item | 06-Jan-19 | 13-Jan-19 | 20-Jan-19 | 27-Jan-19 | 03-Feb-19 | 10-Feb-19 | Total |
| Baseline | |||||||
| Earned | |||||||
| Remaining |
Experts please give me your input.
Regards
Jithin
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?