Report - Manhours Planned Vs Actual

Jithin KambhikanamMember for 15 years 6 months
Created
3
2
0

Hello Everyone,

 

I have made a resource loaded schedule. 

I am looking for report which can Show me Planned Manhours (As per Basline) and Earner Manhours (After Updating the Schedule) and Remianing Manhours (After Updating the Schedule) in Time Distributed Format like below,

Item06-Jan-1913-Jan-1920-Jan-1927-Jan-1903-Feb-1910-Feb-19Total
Baseline       
Earned       
Remaining       

 

Experts please give me your input.

 

Regards

Jithin

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    canned report in P6RE-01

    canned report in P6

    RE-01 Earned Value Units for WBS and Activities

  2. 0
    Jithin Kambhikanam ·

    Hi Zoltan,I dont have such a

    Hi Zoltan,

    I dont have such a report RE-01. Is it done other report. Could you guide me please.

     

    Regards

    Jithin

  3. 0
    Zoltan Palffy ·

    check you email here

    check you email here 