massive project creation

Elisabetta RizzoMember for 7 years 6 months
Created
3
4
0

Hi,

i would like to create a large group of projects in p6. Is there a functionality to create a large amount of simple project in p6? Something like the batch to create financial period?

They must be simple, without activities, because I will edit them one by one.

 

Thanks,

E.

3 replies

Oldest first
  1. 0
    Santosh Bhat ·

    There is no batch feature,

    There is no batch feature, but you can select multiple projects at a time and copy and paste them.

    So 1 copy = 2 projects

    then 4, then 8, then 16, 32, then 64 etc..

  2. 0
    Elisabetta Rizzo ·

    Hi,thank you for your

    Hi,

    thank you for your suggestion, but I need to create different projects (with no activities), with different values for fields as project udfs or project codes. I would like to create a unique file with all projects in order to import it only once. I know that is just a dream. =S I tried with parser, but it is difficult to modify. 

     

    Thanks.

  3. 0
    Rafael Davila ·

    I use different software but