Activity cost as a percentage of the Project Budget Cost
- Created
- 5
- 3
Hi guys, I would like to express an activity cost as a percentage of the project budget cost. For example
Project A - Total Cost is $5000
Project A has numerous activities and I would like a Column that expresses the Cost of the Activities as a percentage of Project A total cost.
For example if Activity 1 within Project A has a total budget cost of say 1000. I would like a column that shows Cost % Budge of Activity 1 as 20%.
I tried using the column "Cost % of Budget" and it was only giving me Zero % ages for every activity.
I would appreciate any form of assistance with this request.