Where to find the Project Codes Table?

Rodney JonesMember for 14 years 4 months
Created
1
1
0

I would like to transfer all the Project Codes from one P6 (R16)PMDB to another P6 (R16)PMDB. How do I find the table/schema?

 

Thanks,

 

Rod

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    project codes or activity

    project codes or activity codes ?

    here is the project code schema

    PROJPCAT
    Columns
    KeyNameTypeDescriptionDefault
    PK,FKproj_idintegerFK to PROJECT table - identifies the project 
    PK,FKproj_catg_type_idintegerFK to PCATTYPE table - identifies the project code type 
    FKproj_catg_idintegerFK to PCATVAL table - identifies the project code value 
     update_datedateRefresh audit field of last date updated. Trigger maintained. 
     update_userstring(255)Refresh audit field of last user updated. Trigger maintained. 
     create_datedateRefresh audit field for date record created. Trigger maintained. 
     create_userstring(255)Refresh audit field for user that created the record. Trigger maintained. 
     delete_session_idintegerDeleted by session id. Client maintained. 
     delete_datedateDeleted date. Client maintained. 

    Indexes
    NameUniqueFields
    ndx_projpcat_pcattypeNONUNIQUEproj_catg_type_id
    ndx_projpcat_pcatvalNONUNIQUEproj_catg_id
    ndx_projpcat_update_date1NONUNIQUEupdate_date
    ndx_projpcat_dsiNONUNIQUEdelete_session_id,delete_date
    ndx_projpcat_updNONUNIQUEupdate_date,delete_session_id

    Triggers
    PRMAUD_PROJPCATORSQL Server 
    RT_PROJPCAT_DELORSQL Server 
    RT_PROJPCATORSQL Server 

    Constraints
    NameTypeFieldsTargetFieldsDelete ruleRefer TypeCondition
    pk_projpcatPRIMARYproj_id,proj_catg_type_id    
    fk_projpcat_pcattypeFOREIGNproj_catg_type_idPCATTYPEproj_catg_type_id DEPENDENT 
    fk_projpcat_pcatvalFOREIGNproj_catg_idPCATVALproj_catg_id DEPENDENT 
    fk_projpcat_projectFOREIGNproj_idPROJECTproj_id DEPENDENT