The F9 is Canceled when i close the project
In the Open Standard
Lyna BellahseneMember for 6 years 11 months
- Created
- 2
- 4
0
Hi everyone,
I have a probleme with a project in P6, the dates ( delta of 1 minute but the date change to the day after ) of about 30 activities (30/1600) changes when i close and re open the project. I think that the problem comes from the excel that we import in order to change the ressources. So when i remove the ressources its all ok but, so i try to add the ressources back... same problem
i tried to add another activities with the same sittings it remains the same.
thanks a lot for ur help!
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?