Imported Project Without Baseline
In the Open Standard
Irfan MorkocMember for 13 years 7 months
- Created
- 2
- 4
0
Hi,
I have imported a file without its baseline. But I see baseline start/finishes dates are different than project start/finish dates. I checked there is no assigned baseline. I expect if there is no baseline assigned to the project then baseline dates should be equal to project dates.
Could you please explain ?
Regards
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?