Imported Project Without Baseline

Irfan MorkocMember for 13 years 7 months
Created
2
4
0

Hi,

I have imported a file without its baseline. But I see baseline start/finishes dates are different than project start/finish dates. I checked there is no assigned baseline. I expect if there is no baseline assigned to the project then baseline dates should be equal to project dates.

Could you please explain ?

Regards

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hi Irfan,Insert the Planned

    Hi Irfan,

    Insert the Planned Start and Planned Finish dates in the gantt chart columns; you should find that these dates are different from Early Start / Finish dates, and the same as Baseline ones.

    When a project has no baseline, planned dates are used instead.

    Years ago, the P6 guru Ron Winter had published a very interesting paper "Understanding P6 dates"; easy to find on the Internet, as I do not know how to share my local file on the forum

    Alexandre

  2. 0
    Irfan Morkoc ·

    Thank you very much

    Thank you very much Alexandre.