Planned Progress for Building Project

Moutaz AldeibMember for 22 years 9 months
Created
1
3
0

Greetings Planners,

Based on what to estimate the planned progress for a building project that includes sub-structure and super-structure items (steel fixing, shuttering, casting, deshuttering, slab on grade ect.

I have quantities for steel and quantities for concrete and the price can not be the factor to estimate planned progress.

Your help is highly appreciated

 

Muataz

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    installation rates should be

    installation rates should be based on estimated quantities and historial company standards also the number of men that are going to perfom the task.

    I can have a task for 80 hours for 1 man to do something whoulcwould be 10 days. However if I put 2 men on that taks it will take 5 days.

    It a combination of estimated manhours and the number of men to use on that task.

Log in or join to reply