Importing an XER to a project - Data date?
In the Open Standard
Tom TurnhamMember for 13 years 1 month
- Created
- 4
- 3
0
Hi Guys,
I wanted to copy some activities over from one project to another but I had to keep the activity IDs the same. The only way I could get that to work was to import the XER into the other project, which did work.
However, everytime I reschedule P6 acts as if I have 2 projects open and gives me the option to use each projects own data date or apply a selected data date to all projects.
Is there a way of getting P6 to think its just one project again?
Cheers,
Tom