XML import failure
In the Open Standard
Rodney JonesMember for 14 years 4 months
- Created
- 2
- 2
0
Hi Everyone,
I am having problems importing two MSP files that are saved as xml format. I have tried on our corporate SQLServer V20 and also on my Standalone SQLite V21.
The V20 import log just says Import: Failed
The V21 import gives me a message as Import Successful but the schedule does not appear in my projects list and the log file says, yep, you guessed it, Import: Failed.
Both times the xml file fails to import. Any ideas? I am happy to share the MSP files for you to play with.
Thanks, RJ