P6 Calendar Import Settings
In the Open Standard
John ReevesMember for 13 years 5 months
- Created
- 1
- 3
0
If you do not choose New for the Calendar on a project update import, could the other setting change the calendars and thus dates on previous updates and the baseline? when do you choose which settings for Calendars. But if I choose new everytime I am going to have a whole bunch of calendars. Sidenote, the default should be project cal. not global, this is such a common error from contractors.
1 reply