Creating bulk activities from excel import
- Created
- 2
- 2
Hello,
It's a bit a basic importing question.
I want to create a bulk duplicate activities in P6. The original activities contain two resources that I want to split for the sake of reporting and leveling. Will creating new lines in excel import suffice to add them in P6?
Example:
Current:
Act ID - Act Name - Res IDs
A0001 - Activity 1 - Res1, Res2
Target:
Act ID - Act Name - Res IDs - Remark
A0001 - Activity 1 - Res1
DUPA0001 - Activity 1 - DUPLICATE - Res2 - Created by excel import
You can suggest another ethod of doing this.
Thanks in advance
2 replies
Oldest firstLog in or join to reply